November 2016 Report
As of November 2016, Dasta Concerto is soon approaching the completion. This report is structured like our last report to make it easy for you to track progress.
Here is the breakdown of the current construction progress
What have we completed?
• East & West wing OHT work is completed.
• Door jambs, touch-up, kitchen area POP and punning work is completed up to 14th floor.
• Door frames in the flats fixed up to 14th floor.
• Electrical wiring, switches and distribution board work completed up to 14th floor.
• Bore packing of sanitary lines is completed up to 14th floor.
• Toilet dado tile work is completed up to 14th floor.
• Sanitary lines have been installed up to 14th floor ceiling.
• Toilet floor tile work is completed up to 14th floor.
• Staircase railing on the east & west wing is completed up to the terrace floor.
• Kitchen cabinets, granite slab and dado tile work completed up to 14th floor.
• Fire staircase door-frames have been fixed up to 14th floor.
• Corridor tile laying work is completed up to 14th floor.
• Screed concrete work in master bed room of the flats has been completed up to 14th floor.
• Swimming pool tile work is completed.
• Jalli is been fixed in the balcony of individual flats up to 14th floor.
• Fire duct wet riser work is completed.
• Plumbing duct work is completed.
• Sump tank work is completed.
• Basement VDF work is completed.
• External paint work is completed.
• East & West wing staircase tile work is completed.
• 8 Passenger lift work is completed.
• Electrical duct wiring work is completed.
• DG installation work is completed.
• Fire pump room work is completed.
• Domestic water sump tank pump fixing work is completed.
• Storm water tank pump fixing work is completed.
• STP pump fixing work is completed.
• Electrical main circuit termination to panel board work is completed.
• Final Coat of paint is completed from 2nd till 12th Floor.
• Main Door Final coat of polish work is completed from 2nd till 12th Floor.
• Bed Room doors & toilet Doors Final Coat of paint is completed from 2nd till 11th floor.
• Corridor Light Fitting is completed from 2nd till 14th floor.
• Main door, Balcony & Utility lights fixing is completed from 2nd till 14th Floor.
• Lift wall granite cladding work is completed.
• Provision for TV, telephone & broadband lines Work is completed.
• Swimming pool area work is completed.
• Children play area work is completed.
• Club house civil work is completed.
• Podium cleaning & water proofing work is Completed.
• Main doors and bed room doors shutter fixing work is Completed.
• Compound wall main gate work is completed.
• RO Plant Work is completed.
• Corridor, Main door, Utility & Balcony Street Pole Light Fitting Work is completed.
• Compound wall, Security cabin Electrical Wiring Work & CCTV Camera Cabling Work is completed.
• CP fitting work is completed.
What is in progress?
• Bed room doors& toilet doors paint work is in progress on 13th floor onwards.
• UPVC sliding doors and windows installation work is in progress on Ground & 1st Floor.
• Quality check of plumbing lines in progress.
• Electrical point’s quality check is in progress.
• Stretcher size passenger lift work is in progress.
• Grid ceiling work for toilet and kitchen utility is in progress.
• Internal flat final coat of paint work is in Progress.
• Cleaning and grouting of floor & toilet tiles is in progress.
• Sign Boards & Display work is in progress.
• HT Work is in progress.
• Landscaping Work is in progress.
• Podium Paver Finish Work is in progress.
• Final Cleaning of Flats for handover work is in progress.
• Sliding folding doors Painting work is in progress.
• FPS Final Fixtures Fitting & Testing Work is in progress.
• Club House Painting Work is in progress.
• Steam Room Work is in progress.
• Ground Floor Lobby Area & Gym Area False Ceiling Work is in Progress.
• Gym, Club House & Main Building Entrance Area Glass Procurement Work is in progress.
[East Elevation]
[West Elevation]
[North West Elevation]
[North Elevation]
[Entry ramp into basement]
[Exit ramp from basement]
[Basement Area]
[Common area corridor]
[Ground level parking area]
[Indoor Games Area]
[Clubhouse – Multipurpose Area]
[Clubhouse – Open Party Area]
[Clubhouse – Outdoor Aerial View]
[Clubhouse – Swimming Pool Area]
[Master Bedroom Wooden Flooring]
[Staircase Area]
[Terrace]