Dec 2014 Report

Construction Update
3rd January, 2015

As of December 2014, construction has reached the 9th floor slab. Progress on site is holding at 15 days ahead of schedule. This report is structured like our last report to make it easy for you to track progress. The photo above should serve as a simple visual progress indicator. Here is the breakdown of the […]

8th Slab Update

Construction Update
17th December, 2014

As of December 17th, 2014, construction has reached the 8th floor slab. Progress is still 15 days ahead of our scheduled date of completion. This is a minor slab update report. You can read the detailed report from Nov 2014. This photo above should serve as a simple visual progress indicator. We will publish a […]

Nov 2014 Report

Construction Update
28th November, 2014

As of November 2014, construction has reached the 7th floor slab. Progress is still 15 days ahead of our scheduled date of completion. In our effort to bring you transparency and convenience, we’ve put together this construction report to help you get an idea of what’s happening at the site. The photo above should serve as a […]

Get a feel of the apartment

29th October, 2014

No matter how specific and elaborate we get with orienting you with Dasta Concerto online, getting a physical feel for the space is essential. The Model Apartment is an ideal experience to spatially orient yourself with the scale and functionality of the apartment. We’ve built a typical 3 BHK apartment and furnished it to give you […]

Oct 2014 Report

Construction Update
17th October, 2014

As of October 2014, construction has reached the 5th floor slab. Progress at the Dasta Concerto site is at an ideal state; we are 15 days ahead of our scheduled date of completion. In our effort to bring you transparency and convenience, we’ve put together this construction report to help you get an idea of […]

www.Lazaro.in - Customer Journey Strategy & Implementation