July 2016 Report
As of July 2016, your apartment is ready for Fit outs. This report is structured like our last report to make it easy for you to track progress.
Here is the breakdown of the current construction progress
What have we completed?
• East & west wing OHT work is completed.
• Door jambs, touch-up, kitchen area POP and punning work is completed from 1st till 14th floor.
• Door frames in the flats fixed up to 14th floor.
• Electrical wiring, switches and distribution board work completed from 2nd till 13th floor.
• Bore packing of sanitary lines is completed from ground till 14th floor.
• Toilet dado tile work is completed from ground till 14th floor.
• Sanitary lines have been installed in ground till 14th floor ceiling.
• Toilet floor tile work is completed from 1st till 14th floor.
• Staircase railing on the east & west wing is completed from ground to the terrace floor.
• Bed room doors & toilet doors putty & 1st Coat of paint work completed from 1st till 13th floor.
• Kitchen cabinets, granite slab and dado tile work completed from 2nd till 11th floor.
• Fire staircase door-frames have been fixed from ground till 14th floor.
• Corridor tile laying work is completed from 1st till 14th floor.
• Screed concrete work in master bed room of the flats has been completed from 1st till 14th floor.
• Swimming pool tile work is completed.
• Jalli is been fixed in the balcony of individual flats up to 14th floor.
• Fire duct wetriser work is completed.
• Plumbing duct work is completed.
• Sump tank work is completed.
• Basement VDF work is completed.
• External paint work is completed.
• East & West wing staircase tile work is completed.
• Passenger lift shaft work is completed.
• Electrical duct wiring work is completed.
• DG installation work is completed.
• Fire pump room work is completed.
• Domestic water sump tank pump fixing work is completed.
• Storm water tank pump fixing work is completed.
• STP pump fixing work is completed.
• Electrical main circuit termination to panel board work is in progress.
What is in progress?
• Bed room doors & toilet doors paint work is in progress.
• Main doors and bed room doors shutter fixing work is in progress.
• UPVC sliding doors and windows installation work is in progress on 13th floor onwards.
• Kitchen slab & dado work is in progress on 12th floor onwards.
• Quality check of plumbing lines in progress.
• Electrical point’s quality check is in progress.
• Passenger lift work is in progress.
• Lift wall granite cladding work is in progress.
• Grid ceiling work for toilet and kitchen utility is in progress.
• Internal flat final coat of primer work is in Progress.
• Cleaning and grouting of floor & toilet tiles is in progress.
• Provision for TV, telephone & broadband lines is in progress.
• HT work is in progress.
• Swimming pool area work is in progress.
• Children play area work is in progress.
• Club house civil work is in progress.
• CP fitting work is in Progress.