October 2016 Report
As of October 2016, your apartment is ready for fit-outs. This report is structured like our last report to make it easy for you to track progress.
Here is the breakdown of the current construction progress
What have we completed?
• East & west wing OHT work is completed.
• Door jambs, touch-up, kitchen area POP and punning work is completed up to the 14th floor.
• Door frames in the flats fixed up to 14th floor.
• Electrical wiring, switches and distribution board work completed up to 14th floor.
• Bore packing of sanitary lines is completed up to the 14th floor.
• Toilet dado tile work is completed up to the 14th floor.
• Sanitary lines have been installed up to 14th floor ceiling.
• Toilet floor tile work is completed up to the 14th floor.
• Staircase railing on the east & west wing is completed up to the terrace floor.
• Kitchen cabinets, granite slab, and dado tile work completed up to 14th floor.
• Fire staircase door-frames have been fixed up to the 14th floor.
• Corridor tile laying work is completed up to the 14th floor.
• Screed concrete work in the master bedroom of the flats has been completed up to the 14th floor.
• Swimming pool tile work is completed.
• Jalli is been fixed in the balcony of individual flats up to 14th floor.
• Fire duct wet riser work is completed.
• Plumbing duct work is completed.
• Sump tank work is completed.
• Basement VDF work is completed.
• External paintwork is completed.
• East & West wing staircase tile work is completed.
• 8 Passenger lift work is completed.
• Electrical duct wiring work is completed.
• DG installation work is completed.
• Fire pump room work is completed.
• Domestic water sump tank pump fixing work is completed.
• Stormwater tank pump fixing work is completed.
• STP pump fixing work is completed.
• Electrical main circuit termination to panel board work is completed.
• Final Coat of paint is completed from 2nd till 11th Floor.
• Main Door Final coat of polish work is completed from 2nd till 12th Floor.
• Bed Room doors & toilet Doors Final Coat of paint is completed from 2nd till 11th floor.
• Corridor Light Fitting is completed from 2nd till 14th floor.
• The Main door, Balcony & Utility lights fixing is completed from 2nd till 14th Floor.
• Lift wall granite cladding work is completed.
• Provision for TV, telephone & broadband lines Work is completed.
• Swimming pool area work is completed.
• Children play area work is completed.
• Clubhouse civil work is completed.
• Podium cleaning & waterproofing work is Completed.
What is in progress?
• Bedroom doors & toilet doors paintwork is in progress on 12th floor onwards.
• Main doors and bedroom doors shutter fixing work is in progress.
• UPVC sliding doors and windows installation work is in progress on the 14th floor.
• Quality check of plumbing lines in progress.
• Electrical point’s quality check is in progress.
• 13 Passenger lift work is in progress.
• Grid ceiling work for toilet and kitchen utility is in progress.
• Internal flat final coat of primer work is in Progress.
• Cleaning and grouting of floor & toilet tiles is in progress.
• CP fitting work is in Progress.
• Sign Boards & Display work is in progress.
• HT Work is in progress.
• Landscaping Work is in progress.
• Podium Paver Finish Work is in progress.
• Corridor, Main door, Utility & Balcony Light Fitting Work is in progress.
• Final Cleaning of Flats for handover work is in progress.
• Sliding folding door work is in progress.
• Compound wall, Security cabin Electrical Wiring Work & CCTV Camera Cabling Work is in progress.
• RO Plant Work is in Progress.
• FPS Final Fixtures Fitting & Testing Work is in progress.
• Club House Painting Work is in progress.
• Steam Room Work is in progress.
• Compound wall main gate work is in progress.
[South Elevation]
[East Elevation]
[West Elevation]
[North West Elevation]
[South West Elevation]
[South East Elevation]
[South Facade]
[Drive way ramp]
[Basement Area]
[Basement Entry & Exit Point]
[Common area corridor]
[Drive way & Ground level parking area]
[Security Room & Boom Barrier]
[Clubhouse Area]
[Multipurpose hall area]
[Indoor Games Area]
[Apartment Living Area]
[Apartment Kitchen Area]
[Apartment Dining Area]
[Apartment Balcony Area]