8th Slab Update
As of December 17th, 2014, construction has reached the 8th floor slab. Progress is still 15 days ahead of our scheduled date of completion. This is a minor slab update report. You can read the detailed report from Nov 2014. This photo above should serve as a simple visual progress indicator. We will publish a detailed construction report when Slab 9 is cast.